Elk Street Reconstruction
Elk Street Reconstruction
Project Description
The Elk Street reconstruction design commenced in 2021. Elk Street is in close proximity to schools, community spaces and ongoing development. The reconstruction of Elk Street provides the ideal opportunity to provide active transportation options to all residents for the foreseeable future and to incorporate modern civil engineering design practices into the design.
The optimal cross-section for the Elk Street design was found to be a multi-use path on the north side, two driving lanes, and a parking lane and sidewalk on the south side of the road (see Figure 1). The proposed cross-section provides many benefits to both the residents in the area and the community as a whole.


The scope for this project generally includes the following:
- Replacement of approximately 1,250 metres of sanitary sewers;
- Replacement of approximately 1,185 metres of storm sewer;
- Replacement of approximately 1,310 metres of watermain and appurtenances;
- Reconstruction of the existing roadway, curb and gutter and sidewalk;
- Multi-use asphalt pathway in north boulevard;
- PXO crossings at Queen St and Victoria St;
- Line markings and Signage;
- Grading and restoration.
The project has been split into 2 phases to minimize the disruption to residents and provide vehicular detour routes around the site (see Figure 2).
Phase 1 of the project is from Talbot Street South to Victoria Street South. Phase 1 substantial completion is July 2, 2025.
Phase 2 of the project is from John Street South to Victoria Street South. The ultimate project completion date for the project is October 31, 2025.

Elk Street Reconstruction News and Notices
- Elk Street Reconstruction Update: April 11, 2025Elk Street Reconstruction Update: April 11, 2025 Location: Elk Street Initial road removals have been completed and temporary watermain has been installed for Phase 1. These are the last items to be completed before underground servicing work (i.e. sewers and watermain) may begin. The contractor is PV-EX Construction Ltd. Work Completed to Date: Work Scheduled for… Continue reading Elk Street Reconstruction Update: April 11, 2025
- Elk Street Reconstruction Update: Phase 1 & Road ClosureLocation: Elk Street – Talbot Street East to Victoria Street South Road Closures and Access: Works Scheduled for March 31-April 4, 2025: Construction Safety: Further construction updates will be provided to residents as the project progresses. Detailed information about the project is also available on the Town project specific website at: www.aylmer.ca/elk-street-reconstruction The Town thanks… Continue reading Elk Street Reconstruction Update: Phase 1 & Road Closure
- Elk Street Reconstruction Update: Pre-Condition Survey March 6, 2025
- Elk Street Construction Update: Vegetation and Tree Removal Notice – March 4, 2026Elk Street Construction Update: Vegetation and Tree Removal Notice – March 4, 2026 The Town of Aylmer will soon be starting road reconstruction on Elk Street that will require tree removals. Scope: Tree Removals Including Stump Grinding Location: Elk Street – Talbot Street East to John Street South Timing: Tentative Start Date – Week of… Continue reading Elk Street Construction Update: Vegetation and Tree Removal Notice – March 4, 2026
- Elk Street Construction Update: February 27, 2025Elk Street Construction Update: February 27, 2025 The Town is excited to announce that preparations for the Elk Street Reconstruction project have commenced. Flagging of the overhead wires and powerlines will be completed over the next few days. This is completed to clearly identify any overhead wires to workers and equipment. The start date for… Continue reading Elk Street Construction Update: February 27, 2025
Contact Town of Aylmer Staff
Director of Infrastructure
519-773-3164
Email