The Building and Planning Departments of the Town of Aylmer have collaborated to prepare a report for Council that provides a development activity update for 2024. The report was presented at the January 22, 2025 Regular Meeting of Council

Summary of Building Department Activity

  • 64 permits issued (July 1, 2024 – December 31, 2024)
  • 92 permits in total were issued in 2024
  • 21 permits issued for 57 total dwelling units (singles, semis, townhomes) for Willow Run
  • 115 new dwelling units were created in 2024
  • AIM Industrial Park had its first permit issued for a 24,000 square foot office/warehouse
Willow Run Subdivision
Centennial Estates Subdivision
Willow Run Subdivision – Hayhoe Homes

Summary of Planning and Development Department Activity

  • Cottonwood Subdivision Phase 2 & 3
    • Residential lots currently under construction for Phase 2 of the subdivision under individual building permits
    • Phase 3 is in the engineering design and review phase for the extension of Cottonwood Boulevard and Aspen Parkway
  • Centennial Estates Subdivision Phase 2B
    • Residential lots currently under construction for Phase 2B of the subdivision under individual building permits
    • Engineered fill completed for complete subdivision phase
  • Willow Run Subdivision
    • 55 single detached residential lots
    • 8 semi-detached lots
    • 13 townhouse residential lots
    • 44-unit vacant land condominium community
    • 9.87 hectares of dedicated parkland
    • 1km of new multi-use pathways from Rotary Park to the new SWM facility
    • Issuance of 21 building permits for a total of 57 dwelling unit permits in 5 months
  • AIM Park – Industrial Development/Employment Lands
    • Fully serviced including watermain, SWM pond, storm sewers, sanitary sewers, utilities and over 1km of new road construction for “AIM Park Way”
    • 14 lots of varying sizes fully serviced for industrial development
    • 2 lots sold
    • 1 lot approved for site plan
  • 335 John Street South
    • 34-unit townhouse condominium site
    • Condos currently being built under individual building permits
    • Landscaping, fencing and final grading of lots currently underway
  • 249 John Street South
    • 13-unit townhouse development with private road and parking
    • Currently under construction
    • Site plan agreement registered, anticipated completion spring 2025
  • 47 AIM Park Way (Block 3) – Southwest Color Plus
    • 2,238.04 m2 new manufacturing facility with associated parking and loading areas
    • Site plan agreement complete, currently under construction
    • Anticipated completion spring 2025
  • 25 Progress Drive – Restaurant Site (Phase 2)
    • 425 m2 building under construction, proposed drive through restaurant and a restaurant
    • Site plan has been completed
  • Site Plan Approval
    • 431 John Street South – 76 unit townhouse development with private road network
    • 69 White Street – REM-Tech Industries Inc. – 1,807.7 m2 building addition to existing manufacturing/industrial
    • 60 Willow Drive – 30-unit townhouse condominium site
  • Zoning By-Law Amendments
    • 78 Spruce Street West
    • 2024 housekeeping amendment to the zoning by-law in effect
  • Minor Variances
    • 187 John Street North
    • 555 John Street North – public hearing to be held January 22, 2025
  • Severances
    • 52 Warren Street – public meeting at Elgin County Land Division Committee to be held on February 26, 2025
  • Pre-Consultations
    • John Street North – 3 properties, proposed commercial and residential development
    • South Street West – institutional expansion
    • Talbot Street West – 2 properties, proposed commercial and institutional expansion
    • Spruce Street East – proposed residential development
    • White Street – proposed industrial development
  • Planning Policy Review
    • Amendment to Ontario Regulation 299/19 – Additional Residential Units
    • Ontario Land Tribunal – change in submissions
    • Provincial Policy Statement, 2024
    • Adopted County of Elgin Official Plan
AIM Park
47 AIM Park Way
25 Progress Drive

Summary of Engineering Activities

  • Review and coordinate various servicing activities as they relate to new development (i.e. replacement of main pump station water service to Town owned lands)
  • Amend pavement management and sidewalk program as necessary with ongoing development activities
  • Review and provide comments on various development applications
  • Issuance and receipt of Road Occupancy Permits and necessary documents
  • Receipt and issuance of Site Alteration Permits
  • Respond to various public and development concerns
Rotary Park Trail Extension

Contact Town of Aylmer Staff

Director of Infrastructure
519-773-3164 ext. 4927
Email

Manager of Planning and Development
519-773-3164 ext. 4915
Email

Chief Building Official
519-773-3164 ext. 4902
Email

2022 Municipal Election By-Laws Bidding Opportunities Aylmer Attractions Business Directory