The Building and Planning Departments of the Town of Aylmer have collaborated to prepare a report for Council that provides a development activity update for 2025. The report was presented at the February 18, 2026 Regular Meeting of Council.

Development Update 2025

Summary of Building Department Activity

  • 92 permits issued (January 1, 2025 – December 31, 2025)
  • 10 single-family dwelling permits issued for Centennial Estates – 5 of which have basement Additional Residential Units
  • 27 permits issued for 73 new dwelling units for Cottonwood (single-family, semi-detached, townhouses)
Centennial Estates Subdivision Phase 2B
Cottonwood Phase 3
Willow Run Subdivision

Summary of Planning and Development Department Activity

  • Cottonwood Subdivision Phase 2 & 3
    • Residential lots current under construction for Phase 2
    • 74 single detached houses constructed or are under construction
    • Phase 3 is the extension of Cottonwood Boulevard and Aspen Parkway and includes 19 single and 16 semi-detached lots
    • Phase 3 has been serviced and is complete to rough road grading. The phase will be ready for building permit issuance in early 2026
  • Centennial Estates Subdivision Phase 2B
    • Residential lots currently under construction for Phase 2B of the subdivision under individual building permits
    • 12 single detached houses are constructed or under construction
  • Willow Run Subdivision
    • The residential subdivision includes:
      55 single detached residential lots
      8 semi-detached lots
      13 townhouse residential lots
      44-unit vacant land condominium community
      9.87ha of dedicated parkland.
    • The subdivision also includes over 1km of new multi-use pathways that were completed through a partnership with the Town from Rotary Park to the new SWM facility.
    • Residential construction on the individual lots has commenced at a rapid pace over 60% of this development has had permits issued in 2025
  • AIM Park Industrial Development/Employment Lands
    • Project has been fully serviced including, watermain, SWM pond, storm sewers, sanitary sewers, utilities and over 1km of new road construction for the new road “AIM Park Way”.
    • 14 lots of varying sizes fully serviced for industrial development
    • Two lots have been sold and developed
  • 47 AIM Park Way (Block 3) – Southwest Color Plus
    •     2,238.04 m2 new manufacturing facility with associated parking and loading areas.
    •     Site plan complete
  • 123 White Street (Block 1) – Stubbe’s Concrete
    • New Redi-mix concrete facility with associated parking and loading areas.
    • Site plan complete
    • Phase 1 includes a temporary Redi-mix plant. Phase 2 will include a permanent facility and building.
  • 25 Progress Drive – Restaurant Site (Phase 2)
    • 425 m2 building with a drive thru restaurants, site plan complete
  • 60 Willow Drive
    • 30-unit rental townhouse site.
    • 6 residential townhouse buildings consisting of 4 to 6 rental units per building currently under construction. Site is nearing completion
  • 335 John Street South
    • 34-unit townhouse condominium site.
    • Condos currently being built under individual building permits.
    • Landscaping, fencing and final grading of lots currently underway.
  • 69 White Street – REM-Tech Industries Inc.
    • 1,807.7 m2 building addition to existing manufacturing/industrial, additional parking and trucking route at this location.
    • Site currently under construction.
  • 555 John Street North – Wendy’s Restaurant
    • 188 m2 1 storey drive through restaurant; development nearing completion
  • 657 John Street North – Shoppers Drug Mart
    • 17056sqft (1584 m2) commercial addition for a new Shoppers Drug Mart store; development currently under construction
  • Site Plan Applications
    • 78 Spruce Street West – 29 townhouse units, site plan approval in process
  • Zoning By-Law Amendments
    • 22 Wellington Street OPA and ZBA – OPA & ZBA in effect
    • 448 Talbot St W / 215 South St W, OPA and ZBA – OPA has been adopted, ZBA has been passed
  • Minor Variances
    • 9 Rebecca Drive – minor variance in effect
    • 45 & 47 Forest Street – minor variance in effect
    • 95 Queen St South – minor variance in effect
    • 71 Rebecca Drive
    • 11 & 13 Pierce Street
    • 104 Aspen Parkway
    • All minor variance listed above are in force and effect
  • Severances
    • 11 & 13 Pierce Street – semi-detached residential lots have been approved and created
    • Menno Lodge Phase 2 – severances have been conditionally approved
  • Pre-Consultations
    Collectively, the Director of Operations & Infrastructure, Chief Building Official, Manager of Planning and Development and as well as the Director of Emergency Services/Fire Chief have been actively engaged in holding pre-consultation meetings for possible future site plan applications and other planning applications for the following:
    • Cherry St Affordable housing multi residential, 103 Sydenham St W
    • Expansion of commercial uses EIC – 516 John St N
    • New seniors Apt building – Caverly Road
  • Policy Planning Review
    The Planning and Development Department has been actively reviewing new provincial planning policies:
    • Fighting Delays, Building Smarter Act, 2025 (Bill 60, not in effect yet)
    • Updates to the Ontario Heritage Act
657 John Street North – Shoppers Drug Mart
555 John Street North – Wendy’s Restaurant
123 White Street – Stubbe’s Concrete

Summary of Engineering Activities

  • Review and coordinate various servicing activities as they relate to new development (i.e. replacement of main pump station water service to Town owned lands)
  • Amend pavement management and sidewalk program as necessary with ongoing development activities.
  • Review and provide comments on various development applications:
    • Storm water management calculation review
    • Low impact Development review (storage for 2-to-100-year storm capacity)
    • Sanitary design calculation review
    • Water modeling review
    • Development, roadway, and lot grading review
    • Servicing Easement requirements
    • Private and public parking requirements
    • Landscaping requirements
    • Lighting requirements as per RP-8-14
    • AODA requirements
  • Issuance and receipt of Road Occupancy Permits and necessary documents (i.e., Utility contractors, Servicing in the Town ROW, etc.)
  • Receipt and issuance of Site Alteration Permits
  • Respond to various public and development concerns

Contact Town of Aylmer Staff

Director of Operations and Infrastructure
519-773-3164 ext. 4927
Email

Manager of Planning and Development
519-773-3164 ext. 4915
Email

Chief Building Official
519-773-3164 ext. 4902
Email