The Building and Planning Departments of the Town of Aylmer have collaborated to prepare a report for Council that provides a development activity update for 2025. The report was presented at the July 9, 2025 Regular Meeting of Council.

Summary of Building Department Activity

  • 52 permits issued (January 1, 2025 – July 1, 2025)
  • 13 permits issued for 38 total dwelling units (7 singles, 31 townhomes) for Willow Run
  • 5 permits issued for single family dwellings for Cottonwood
Willow Run Subdivision
Cottonwood Subdivision
Centennial Estates

Summary of Planning and Development Department Activity

  • Cottonwood Subdivision Phase 2 & 3
    • Residential lots under construction for Phase 2 of the subdivision under individual building permits
    • 24 single detached houses have been constructed to date
    • Phase 3 is in the engineering design and review phase for the extension of Cottonwood Boulevard and Aspen Parkway
  • Centennial Estates Subdivision Phase 2B
    • Residential lots currently under construction for Phase 2B of the subdivision under individual building permits
    • 6 single detached houses are currently under construction
    • Engineered fill completed for complete subdivision phase
  • Willow Run Subdivision
    • 55 single detached residential lots
    • 8 semi-detached lots
    • 13 townhouse residential lots
    • 44-unit vacant land condominium community
    • 9.87 hectares of dedicated parkland
    • 1km of new multi-use pathways from Rotary Park to the new SWM facility
    • Residential construction on the individual lots has commenced at a rapid pace with the construction of 66 units
  • AIM Park – Industrial Development/Employment Lands
    • Fully serviced including watermain, SWM pond, storm sewers, sanitary sewers, utilities and over 1km of new road construction for “AIM Park Way”
    • 14 lots of varying sizes fully serviced for industrial development
    • 2 lots sold
  • 335 John Street South
    • 34-unit townhouse condominium site
    • Condos currently being built under individual building permits
    • Landscaping, fencing and final grading of lots currently underway
  • 47 AIM Park Way (Block 3) – Southwest Color Plus
    • 2,238.04 m2 new manufacturing facility with associated parking and loading areas
    • Site plan agreement complete, currently under construction
  • 25 Progress Drive – Restaurant Site (Phase 2)
    • 425 m2 building under construction, proposed drive through restaurant and a restaurant
  • 123 White Street – Stubbe’s Concrete
    • New redi-mix concrete facility with associated parking and loading areas
    • Site plan agreement complete, currently under construction
    • Phase 1 includes a temporary redi-mix plant
    • Phase 2 will include a permanent facility and building
  • 69 White Street – REM-Tech Industries Inc.
    • 1,807.7 m2 building addition to existing manufacturing/industrial, additional parking and trucking route at this location
    • Site currently under construction
  • 60 Willow Drive
    • 30-unit rental townhouse site
    • Servicing for the townhouse site has been completed and under construction through individual building permits
    • 5 residential townhouse buildings consisting of 4 to 6 rental units per building currently under construction
  • Site Plan Approval
    • 555 John Street North – drive through restaurant, site plan is complete
    • 123 White Street – Stubbe’s Precast, site plan complete, under construction
    • 78 Spruce Street West – 29 townhouse units, site plan approval in process
  • Zoning By-Law Amendments
    • 22 Wellington Street OPA and ZBA – OPA adopted, awaiting County approval; ZBA will come into effect once OPA has been approved
    • 2025 housekeeping amendment to the zoning by-law in effect
  • Part Lot Control Exemptions
    • Willow Run Subdivision
  • Minor Variances
    • 555 John Street North – minor variance in effect
    • 9 Rebecca Drive – public hearing July 9, 2025
  • Severances
    • 52 Warren Street – residential lots have been created and registered
    • 45 & 47 Forest Street – residential lots conditionally approved
    • 11 & 13 Pierce Street – public meeting August 27, 2025
  • Pre-Consultations
    • John Street North – commercial expansion
    • Talbot Street East and South Street West – medium density residential expansion
    • Spruce Street East – industrial development
  • Planning Policy Review
    • Protect Ontario by Building Faster and Smarter Act, 2025 (Bill 17)
    • Protect Ontario by Unleashing our Economy Act, 2025 (Bill 5)
69 White Street
47 Aim Park Way
335 John Street South

Summary of Engineering Activities

  • Review and coordinate various servicing activities as they relate to new development (i.e. replacement of main pump station water service to Town owned lands)
  • Amend pavement management and sidewalk program as necessary with ongoing development activities
  • Review and provide comments on various development applications
  • Issuance and receipt of Road Occupancy Permits and necessary documents
  • Receipt and issuance of Site Alteration Permits
  • Respond to various public and development concerns

Contact Town of Aylmer Staff

Director of Operations and Infrastructure
519-773-3164 ext. 4927
Email

Manager of Planning and Development
519-773-3164 ext. 4915
Email

Chief Building Official
519-773-3164 ext. 4902
Email

2026 Municipal Election By-Laws Bidding Opportunities Aylmer Attractions Business Directory